71、The ETL tochnology is mainly ued in (71) stage.
A. data collection
B. data storage
C. data management
D.data analysis
72、(72) is not used on perception layer of Internet of Things.
A. WLAN
B. RFID
C. Bluetooth
D.SOA
73、The (73) is a hierarchical docomposition of the total scope
of work to be carried out by the project team to accomplish the project ob jectives
and create the requirod deliverable.
A.0BS
B. WBS
C. RBS
D. RAM
74、(74) is a measure of schedule performance expreessed as the difference between the earned value and the planned value.
A. Schedule varlance (SV)
B. Cost varlance (CV)
C. Actual cost (AC)
D. Earned value (EV)
75、(75): information is not disclosed to unauthorized
indivi duals.
A. Authenticity
B. Integrity
C. Availability
D. Confidentiality